Vertical Gravity take-up ststaion

Posted in: , on 6. Dec. 2005 - 07:06

We have a belt conveyor in which vertical gravity take-up is provided. The take-up station is provided with two pulleys with two counter weights adjacent to each other. This arrangement is provided as there is not enough space for horizontal take up. Belting endless length is 901 m. We are faced with a problem. When we start the belt conveyor, the first VGT pulley (towards the drive pulley) goes down and hits the ground and the second VGT pulley goes up. This happens when the counter weight is same in both the counter weight boxes. If the counter weight is reduced by even 50 Kgs from the counter weight box 1 and added to counter weight box no. 2, the situation reverses.

Due to the above problem we are not able to run this belt conveyor. Request all of you to share the experience to solve this problem.

N. K. Kabra Manager - Projects, G4 IInd Floor, Gate No. 1, Powai Works, Larsen & Toubro Limited, Mumbai - 400 072 India

Re: Vertical Gravity Take-Up Ststaion

Posted on 6. Dec. 2005 - 06:41

You cannot have two independent takeup masses working for the reasons you just experienced. You may be able to connect them together to obtain proper functionality, but more information is required. The check list may be long based on how your design has evolved. A thorough check of the design details are in order.

1. What is the criteria for the takeup mass: a) drive slip, b) belt sag, c) dynamics, d) other

2. What is the criteria for the takeup travel: a) tension range for loaded and empty belt, b) thermal range, c) permanent belt stretch, d) belt sag allowance, e) belt splice allowance for repair, f) clearances between upper and lower travel stops, g) other conditions which may need inclusion

2. MY opinionn is you need professional advice beyond that which can or shoiuld be offered by the forum members as advice. THere are too many "what if" conditions to be answered that will guarantee success with safety.

3 Who ever recommended your applied design does not understand the basic physics and calls into question the design's proper development. Get help.

4. I can assure you there are more than 30 major questions that need to be reviewed to give your design a OK including mechanical, electrical, structural, electrical, and control w/ instrumentation.

Lawrence Nordell Conveyor Dynamics, Inc. website, email & phone contacts: www.conveyor-dynamics.com nordell@conveyor-dynamics.com phone: USA 360-671-2200 fax: USA 360-671-8450

Re: Vertical Gravity Take-Up Ststaion

Posted on 6. Dec. 2005 - 06:56

Your question has merit. I have been in discussions with other engieers which ponder the same question, without thinking the outcome through as an engineer should.

The first counterweight takeup (TU) will fall first as you see when the two TU's have balanced masses because the pulleys following after the first TU require added belt tension to pull the belt around these following pulleys with their bearing and seal drag resistance. THe higher belt tension, at the second TU, exceeds the mass of the second TU mass which cause the TU to rise.

By increasing the second TU mass by 50 kg, this is apparently sufficient to overcome the pulleys' drag and belt bending with the result it has enough mass to overcome the mass of first TU thereby lifting ithe first TU as the second TU mass falls.

Lawrence Nordell Conveyor Dynamics, Inc. website, email & phone contacts: www.conveyor-dynamics.com nordell@conveyor-dynamics.com phone: USA 360-671-2200 fax: USA 360-671-8450

Re: Vertical Gravity Take-Up Ststaion

Posted on 6. Dec. 2005 - 07:07

Question:

I drove by your Mumbai offce and noticed its was not far from the convention center where the Bulk Solids Asia 2005 conference was held. I did not see or meet anyone from Larsen Toubro.

It would have been a pleasure to meet with you and discuss the nature of such problems.

There were many experts from around the world who took their time to come to India and share their research work and design experiences with you. What happened to L & T attendance?

Lawrence Nordell Conveyor Dynamics, Inc. website, email & phone contacts: www.conveyor-dynamics.com nordell@conveyor-dynamics.com phone: USA 360-671-2200 fax: USA 360-671-8450

Re: Vertical Gravity Take-Up Ststaion

Posted on 12. Dec. 2005 - 12:23

Hello nkkabra..

We quite often use double reaved vertical gravity take-ups. Sometimes because of space restrictions. The last one we did, we needed extra movement as the conveyor had a moving head facility.

We simply use two take-up pulleys on a single take-up box.

That's what you need.

Regards

LSL Tekpro

Graham Spriggs

Re: Vertical Gravity Take-Up Ststaion

Posted on 12. Dec. 2005 - 04:45

nkkabra:

Presumably, you need two take-up pulleys due to space limitations. Depending on the movement required and travel room, you can change this to either one functioning take-up or keep it as two take-ups.

If there is sufficient space to allow for the required take-up travel by one pully, you can fix one of the take up pulleys (trailing one preferred) so that it cannot move and use the other for the take-up action. This allows you to retain belt in the system for splice/repair needs.

If you need the movement of both pulleys, you can do as both Larry Nordell and Graham Spriggs have advised. That is, tie the two travelling pulleys togeter so that they move as a single unit with a bend pulley between them.

The critical action is to do what Larry Nordell advised - have a conveyor expert conduct a site or engineering evaluation as a first step.

Regards,

Dave Miller ADM Consulting 10668 Newbury Ave., N.W., Uniontown, Ohio 44685 USA Tel: 001 330 265 5881 FAX: 001 330 494 1704 E-mail: admconsulting@cs.com

Re: Vertical Gravity Take-Up Ststaion

Posted on 12. Dec. 2005 - 04:49

Dear Shri N K Kabra,

When you have insufficient head room generally one provides horizontal loop gravity take-up. Now, you have already provided dual vertical take-up. In such vertical take-up, there are two take-up pulleys mounted on common frame attached to common counterweight. So, you will have a two take-up pulley and three bend pulleys. Such take-p is working in Malaysian power station for stockyard conveyor equipped with bucket wheel on boom stacker cum reclaimer.

When two take-ups are independent, they will not have exact balanced movements in varied situations, which are very large in numbers; and this can create complication.

Earlier respondents have already explained the situation.

Regards,

Ishwar G Mulani.

Author of Book : Engineering Science and Application Design for Belt Conveyors.

Author of Book : Belt Feeder Design and Hopper Bin Silo

Advisor / Consultant for Bulk Material Handling System & Issues.

Email : parimul@pn2.vsnl.net.in

Tel.: 0091 (0)20 25882916

Re: Vertical Gravity Take-Up Ststaion

Posted on 12. Dec. 2005 - 08:26

Seems to me U have the following options

Join the counterweight frames together - physically or via a rope/sheave system

Fix one GTU and have one in use - if belt stretch etc permits

Go to the different TU arrangement ie inclined with GTU tower outside belt line

Suggest giving your designer a call as well...

Thanks

James

Re: Vertical Gravity Take-Up Ststaion

Posted on 12. Dec. 2005 - 09:46

Even though everyone has done a great job in describing what you need, they say a picture is worth a thousand words.

So I am attaching a drawing of a system that we converted from a single take-up pulley to a double take-up when we changed the belt from a cable belt to a ply belt.

We used the existing CWT box and added a smaller on each side of the existing. Remember that you will need to double the weight in your counteweight box from that of a single CWT.

Good luck with your project.

Gary Blenkhorn

Attachments

805 conveyor (ZIP)

Gary Blenkhorn
President - Bulk Handlng Technology Inc.
Email: garyblenkhorn@gmail.com
Linkedin Profile: http://www.linkedin.com/in/gary-blenkhorn-6286954b

Offering Conveyor Design Services, Conveyor Transfer Design Services and SolidWorks Design Services for equipment layouts.

RAjeev
(not verified)

Takeup

Posted on 14. Dec. 2005 - 01:18

Dear kabra

I hope you have solved the problem by viewing valuable suggestions / hints given above members.

In case you still need any help pl indicate. Sometimes designer does not understand the complications as happened in this case

Mr Nordell correctly explained this is simple physics

Rajeev

Re: Vertical Gravity Take-Up Ststaion

Posted on 18. Dec. 2005 - 03:43

How do these things get through to manufacture? Does, or can, nobody check drawings anymore?

John Gateley johngateley@hotmail.com www.the-credible-bulk.com

Re: Vertical Gravity Take-Up Ststaion

Posted on 19. Dec. 2005 - 06:39

We have solved the problem. I may menntion that due to some reasons the drawing could not be corrected during drawing approval execise. The conveyor is running fine after connecting pulleys and counterweights.

Regards,

N. K. Kabra Manager - Projects, G4 IInd Floor, Gate No. 1, Powai Works, Larsen & Toubro Limited, Mumbai - 400 072 India
nickiemae
(not verified)

Re: Vertical Gravity Take-Up Ststaion

Posted on 13. Jan. 2006 - 02:22

thanks for the info everyone.. a thank you is all i can give..