when on the condition, normal operation and suddenly stop, the belt tension between the two rollers are how to find?Could you provide ideas or formula or reference for calculating. On addition,there are doubled rollers.
Q=3500 t/h
L=1754 m
=17 Deg
H=480.38 m
B=1800 mm
V=5.6 m/s
ks=6300 N/mm
p=4x2000 KW
drum Rt=1.02m
And nameplate torque of the backstop is 100KN.M,the length of torque arm is 2.2m...
And also, the spring system to share the load is necessary,pls give your precious experience and advice!
Belt Tension Calculation
How to calculate this?
Dear all,
when on the condition, normal operation and suddenly stop, the belt tension between the two rollers are how to find?Could you provide ideas or formula or reference for calculating. On addition,there are doubled rollers.
Q=3500 t/h
L=1754 m
=17 Deg
H=480.38 m
B=1800 mm
V=5.6 m/s
ks=6300 N/mm
p=4x2000 KW
drum Rt=1.02m
And nameplate torque of the backstop is 100KN.M,the length of torque arm is 2.2m...
And also, the spring system to share the load is necessary,pls give your precious experience and advice!
Bst Rgds! ■