Double drive systems

Posted in: , on 2. Apr. 2008 - 15:56

Dear Sir/Medam,

I would like to know why a double drive system is used in some designs for ball mills or bucket elevators what are the benefits of using a double drive system over a single drive system,

Regards,

Yogesh

Re: Double Drive Systems

Posted on 2. Apr. 2008 - 04:57

On a bucket elevator maybe it's just a matter of getting the required power into the shaft and on to the pulley/wheels??

Lyle Brown
(not verified)

Re: Double Drive Systems

Posted on 3. Apr. 2008 - 08:26

Maybe along the considerations as for most drives:

With one drive:

Motor failure = no output

With two drives:

One drive failure = probably more than no output

Need to consider space / CAPEX (electrical etc) / OPEX and availiability etc.

Regards,

Lyle

Two Drives Vss One Drive

Posted on 3. Apr. 2008 - 10:15

Hello,

The choice is usually cost - both item costs and inventory costs. Sometimes two gearmotors added is less in cost than a single unit of same power/ speed rating.

Sometimes there are mechanical issues - a flexure suspended feeder for example . For large feeders in flexure suspension - two gearmotors are needed - else the frame gets twisted on one side.

Benukrishna Mandal Management and Engineering Advisor Email : rch_kaapribe@sancharnet.in
Axel Witt
(not verified)

Re: Double Drive Systems

Posted on 4. Apr. 2008 - 12:01

Dear Sir,

in addition to the answers given above I would like to add that it makes sense in certain cases to split the necessary power required for a belt conveyor in a ratio of 2:1 on two drive pulleys. If for example 750 kW have two be installed for a conveyor you can place 500 kW (or better 2x250 kW) on the primary drive pulley and 250 kW on the secondary pulley; you will have identical drives, which could be also installed on other conveyors. Plus, the drives are smaller and easier (and cheaper) to ship and to install.

Regards,

Double Drive Systems

Posted on 4. Apr. 2008 - 12:19

Dear All

I'am very greatfull for your valuable inputs

Regards,

Yogesh

Lyle Brown
(not verified)

Re: Double Drive Systems

Posted on 4. Apr. 2008 - 02:34

Originally posted by Axel Witt

Dear Sir,

in addition to the answers given above I would like to add that it makes sense in certain cases to split the necessary power required for a belt conveyor in a ratio of 2:1 on two drive pulleys. If for example 750 kW have two be installed for a conveyor you can place 500 kW (or better 2x250 kW) on the primary drive pulley and 250 kW on the secondary pulley; you will have identical drives, which could be also installed on other conveyors. Plus, the drives are smaller and easier (and cheaper) to ship and to install.

Regards,

This may also help reduce the UTS of the belt also?

T2 for 250 kW in lieu of 750 kW.

Availibility and CAPEX may cop a hiding though.

Regards,

Lyle

Double Drive Systems

Posted on 5. Apr. 2008 - 07:19

Drive units may be modularized:

1. to simplify inventory. One drive unit may be used in single or multiples throughout a plant, mine, port, etc.

2. for reason mentioned, to minimize T2 in case of dual pulley drives

3. to allow increase in production over time. A system may only need to achieve full production years after initial operation. Modularizing drives allows the addition of power as it becomes required.

The last case was employed at a major slope belt from an underground coal mine.

Joe Dos Santos

Dos Santos International 531 Roselane St NW Suite 810 Marietta, GA 30060 USA Tel: 1 770 423 9895 Fax 1 866 473 2252 Email: jds@ dossantosintl.com Web Site: [url]www.dossantosintl.com[/url]