Procedure for Acceptance Test

Posted in: , on 19. Dec. 2009 - 19:39

Hi,

What is the normal procedure for a typical grinding performance test? Is an engineering consultant required to inspect the test?

Also say, we purchase the mill and classifier to grind d95 = x and d50 = y.

During the performance test, we found out that d95 = x1 and d50=y1, should the plant be rejected or accepted?

And how many test run to allow enough trials for supplier to conclude the acceptance/reject.

Thanks

Re: Procedure For Acceptance Test

Posted on 20. Dec. 2009 - 03:41

Fleetwoodjazz,

I can provide guidance on this issue, however, it is not a black and white, or yes or no answer, so we will need to discuss the details. Please feel free to contact me at any of the methods below.